Independent contractor: OLA 1957

Cards (6)

  • What section of the OLA 1957 is the defence of an independent contractor found?
    s2(4)
  • What is the defence of an independent contractor?
    The lawful visitor has been harmed whilst on the occupier's premises but it has arisen from the negligence of a workman
  • What three requirements must be ALL be satisfied?
    1 . Must be reasonable for the occupier to have given the work to a independent contractor (Haseldine)
    2 . Contractor must be competent - carry out checks (Bottomly)
    3 . Occupier must check work has been properly done - may require an expert (Woodward)
  • What first requirement must be satisfied?
    Must be reasonable for the occupier to have given the work to a independent contractor (Haseldine)
  • What second requirement must be satisfied?
    Contractor must be competent - carry out checks (Bottomly)
  • What third element must be satisfied?
    Occupier must check work has been properly done - may require an expert (Woodward)