Critical Path Analysis
Calculating the Float
Save
Share
Learn
Content
Leaderboard
Share
Learn
Created by
izzy
Visit profile
Cards (2)
Float time
is the amount of time that no
critical activities
with a
project
can be delayed without affecting the project as a whole
Total
float
of an activity =
LFT
-
EST
-
Duration