Activity types include
Fixed Duration
,
Fixed Units
,
Fixed Work
, and
Effort driven.
In a
Fixed Duration
Activity, the work must be completed in a
determined duration.
In a
Fixed Units Activity
, the work must be completed using
determined assigned units.
In a
Fixed Work Activity
, the
work value
is determined.
A Fixed work activity is by
default effort driven.
In an
Effort Driven Activity
, the work value is
fixed.
A
Fixed
work activity could be
Effort
driven or
Non-effort
driven.
If the
assigned units
(U) are
increased
or
decreased
in an
Effort
driven activity, the
duration
(D) will be
decreased
or
increased
respectively.