What is a network analysis?
A project management tool that helps businesses
plan
, schedule and optimise tasks to complete a strategy efficiently
What is the critical path in a network analysis?
The
longest
sequence of
dependant
activities that determines the
shortest
time needed to complete a
project
What is float time in network analysis?
The extra time an activity can
overrun
without
delaying
the overall project completion
time
How is float time calculated?
Latest finish time
-
duration
-
earliest start time
How does network analysis improve efficiency?
It helps managers save
time
, order
resources
just in time, and improve
cash flow
How does network analysis link with delegation?
It allows managers to delegate tasks as the managers know the
start
times,
durations
, and
deadlines
, ensuring
progress
is monitored effectively
If an activity is on the critical path and overruns, what impacts would this have?
Delays
the entire project
Increased
costs
Damage to
reputation
Supply chain
disruptions
If an activity is on the critical path and overruns, why might this increase costs?
Higher
labour
costs (e.g.
overtime
)
If the project is a product launch this could lead to missed market
opportunities
, lost
sales
and a reduced
competitive
advantage
Extended use of rented
equipment
or
facilities
If an activity overruns and is on the critical path, why might there be supply chain disruptions?
If the project is linked to other processes (e.g.
production
schedules), delays can cause widespread
operational
issues
If an activity is on the critical path and overruns, why might this damage reputation?
Late completiton can harm relationships with clients,
suppliers
, and
stakeholders
If an activity has float time and overruns, what impacts could this cause?
Project may still be on
track
Reduced
flexibility
Resource
rescheduling
If an activity overruns and has float time, why does this reduce flexibility?
If float is used up, future
delays
in the same task will impact the project
completion
date
If an activity has float time and overruns, why might this cause resource rescheduling?
Managers may need to rellocate
resources
from other
tasks
to compensate
What are the limitations of using a network analysis?
Network analysis often relies on
estimates
and
forecasts
-significant
research
is required prior
Network anaysis does not guarantee the
success
of the project
Very lengthy or complex projects involve a large number of
activities
that have numerous
dependencies