con 2

Cards (9)

    • Cost increases due to variations are minimized
    • Operating the traditional procurement system can be expensive due to the number of professionals involved
    • Quality:
    • Provides a high degree of quality certainty and functional standards
    • Sufficient time available for client and consultants to review and fully develop design and specifications
    • However, does not provide opportunities for contractors to contribute construction technology and management expertise, which may affect workmanship quality
  • Effects of the traditional procurement system on project performance:
    • Time:
    • Due to its chronological approach, the traditional procurement system is recognized as the slowest project delivery approach
    • More time available for the client and project team to scrutinize and review the design before construction
    • Cost:
    • Provides more price certainty to the client before construction begins because designs are fully completed
    • Gives the client a more competitive price by eliminating design and construction ambiguity that causes contractors to inflate prices
  • When to use traditional/separated procurement system:
    • Best used when time for commencement and completion is not as critical as overall cost, quality, and function of the project
    • Client exercises control over quality, aesthetics, and utility of the project through client's design consultants
    • Variations or changes in scope and quality of the project are often allowed but at the client's risk
  • Approaches to traditional procurement system:
    • Bill of firm quantities:
    • Client selects architect/engineer to design based on client's brief and quantity surveyor prepares a bill of quantities
    • Contractors invited to submit tenders in competition, and the contract is awarded to the most responsive tender
    • Features of bill of firm quantities:
    • Quantities and unit rates form part of the contract
    • Design is virtually completed before signing the contract
    • Merits of bill of firm quantities:
    • Project fully designed before tenders are solicited, removing contingencies during construction
    • Quality in the construction project can be controlled using working drawings and specifications
    • Demerits of bill of firm quantities:
    • Process is slow due to sequential nature
    • Client cannot be certain about the actual cost until tenders are received
    • When to use bill of firm quantities:
    • Where time is not a constraint and quality, aesthetics, and utility are priorities
    • When time is not available after design completion to measure detailed quantities
  • Approximate bill of quantities:
    • Quantities used are approximate and subject to re-measurement during construction
    • Only unit rates are binding on the contractor, and quantities are provisional
    • Merits of approximate bill of quantities:
    • Construction can begin earlier
    • Extra expense of preparing firm quantities can be saved
    • Demerits of approximate bill of quantities:
    • Cannot give the client a realistic total cost of the project
    • Work may prove more costly than if detailed quantities were measured initially
    • When to use approximate bill of quantities:
  • Drawings and specifications methods:
    • Mostly used in the United States of America
    • Contractors prepare their own quantities from drawings before estimating project cost
    • Merits of drawings and specification methods:
    • Cost of engaging quantity surveyor for bills of quantities is eliminated
    • Risk of inaccurate measurement shifted to the contractor
    • Demerits of drawings and specification methods:
    • Evaluation of variations may present problems without bills of quantities
    • Period of tendering is longer as contractors must do their own measurement
    • Features of schedule of rates methods:
    • Similar to using bills of approximate quantities
    • Contracts resulting are referred to as Measurement Contracts or Measured Contracts