Advance notice to the Administrative Authority that the work is ready for inspection.
3 meters
Head of water to be filled on each section of pipings under water test.
15 minutes
Duration that water shall be kept before the start of inspection.
34.5 kPa
Gauge pressure for air test, equivalent to 254 mm Mercury in height.
15 minutes
Duration that air pressure shall be held during air test without introduction of additional air.
344.5 kPa
Air pressure which may be substituted for the water test
50% Water piping
shall be tested under a water pressure not less than the
working pressure
under which it is to be used plus