Smooth and level ground

Cards (6)

  • On a smooth and level area' mark point A and B to be measured.
    1
  • Rear tape man should mark 30m at station A while the head tape man takes the 0 end of the engineer's tape.
    2
  • Same goes with the next rod until it reaches point B' 30m on the rod the 0 on the next.
    3
  • Before it reaches pont B' there will be partial length that will not be exactly 30m.
    4
  • Repeat the process's on line BA.
    5
  • Record the total measurement per line' then complete the tabulated data.