Smooth and level ground
Save
Share
Learn
Content
Leaderboard
Learn
Created by
Antonette Palad
Visit profile
Cards (6)
On a smooth and level area' mark point A and B to be measured.
1
Rear tape man should mark 30m at station A while the head tape man takes the 0 end of the engineer's tape.
2
Same goes with the next rod until it reaches point B' 30m on the rod the 0 on the next.
3
Before it reaches pont B' there will be partial length that will not be exactly 30m.
4
Repeat the process's on line BA.
5
Record the total measurement per line' then complete the tabulated data.
6