  • Discharge of contract - contract comes to an end
  • Both parties have done their side
  • Cutter v powell
    crew member died mid voyage
    wife entitled to no owed wages
    performance not completed
  • Re Moore & co v landaeur & co
    agreement for 30 tin case sale of 3000
    had 3000 but only 24 cases
    not completed exact performance
  • time of performance
    not usually enough
    union eagle v golden achievement - perishable goods, time of performance critical
  • Prevention of performance
    planche v colburn - author entitled to payment - prevented from carrying out contract
  • Accepted part performance
    sumpter v hedges - d had to pay for materials, had no choice but to finish
  • Divisible contracts
    Ritchie v Atkinson - entitled to cargo he did deliver
  • Substantial performance
    only use if not entire contract
    dakin v lee - paid for work minus what it cost to re-do some bits
    bolton v mahadeva - 69% complete, not substantial, entitled to no money
  • Remedy
    damages
    repudiation
    specific performance - court orders job to be finished