Objectives of designing product Layouts/ Line Balancing/ Designing Process Layouts
Solvesimpleline-balancingproblems
Developsimpleprocess and productlayouts
process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements
Line balancing
Goals of Line Balancing:
This minimizes the idle time along the line and results in a high utilization of labor and equipment
lines that are perfectly balanced will have a smooth flow of work as activities along the line are synchronized to achieve maximum utilization of labor equipment
Major obstacles to attaining a perfectly balanced line
It may not be feasible to combine certain activities into the same bundle, either because of differences in equipment requirements or because the activities are notcompatible
Differences among elementaltasklengths cannot always be overcome by grouping tasks
The required technologicalsequence ma prohibit otherwise desirable task combinations
is the maximum time allowed at each workstation to complete its set of tasks on a unit
cycle time
Maximum cycle time is given by the summation of the task times
Minimum cycle time is given by the longest of the task times
The minimumcycle time would apply if there were five workstations
The maximumcycletime would apply if all tasks were performed at a single workstation
As a general rule, the cycle time is determined by the desired output. If the cycle time does not fall between the maximum and minimum bounds, the desired output rate must be revised
A very useful tool in line balancing is a precedence diagram
Determining the maximum output
A) OT / CT
B) CT / D
a very useful tool in line balancing is a precedencediagram. A diagram that shows elementaltasks and their precedencerequirements
tool used in line balancing to display elemental as and sequence requirements
precedencediargram
fill the boxes
A) CT
B) Sum of task time
C) sum of task time
there is another rule called the order of greatestpositional weight
how do you calculate the percent idle time?
Idletime over the number of workstations times cycle time, then multiply to 100%
three basic steps of designing process layout
Gatherinformation
Develop a block plan
Design a detailedlay-out
Step 1. Gather information
Space requirements by center
Availablespace
Closenessratings
A RELchart( REL is short for relationship)
other considerations
Space Requirements
itemizes the specific equipment and space needed for each center, then adds enough circulation space to provide for aisles and the like.
Circulation space may consume at least 25 percent of the center's total space
Available space
a blockplan is a rough space allocation for each department and indicates its placement
the plan need only provide the facility's dimensions and spaceallocation
Closeness Ratings
the layout designer must also know which centers need to be located close to one another
From-to matrix or a REL chart provides the needed information--this matrix gives the numberoftrips between each pair of departments