3.10 Managing Strategic Change
Network (Critical Path) Analysis
Save
Share
Learn
Content
Leaderboard
Share
Learn
Created by
olly tonks
Visit profile
Cards (19)
What is another name for network analysis?
Critical Path Analysis
(
CPA
)
View source
What is the main purpose of Critical Path Analysis?
To identify the
longest path
in a project
View source
How does CPA help in project completion?
It determines the
shortest
time for completion
View source
Why is CPA important for businesses?
It aids in planning
complex
,
high-risk
projects
View source
What type of projects commonly use network analysis?
Construction projects
View source
What are the three essential components needed for CPA?
Activities
,
durations
, and dependencies
View source
What does 'duration' refer to in CPA?
The
time
each
activity
will
take
View source
What are dependencies in the context of CPA?
Activities that must be
completed
first
View source
What is the critical path in a project?
The longest path of
planned activities
View source
Why can't activities on the critical path be delayed?
They would extend the project's
completion time
View source
What is the earlier start time (EST) in a network diagram?
The earliest time an activity can start
View source
How is the latest finishing time (LFT) determined?
By working backwards from the
project end
View source
What does float mean in project management?
The
time
an
activity
can
be
delayed
View source
How is float calculated?
LFT
-
Duration
- EST
View source
What does it mean if an activity has zero float?
It cannot be delayed without
project delay
View source
What happens if any activity on the critical path is delayed?
The overall
project completion time
is delayed
View source
What are the four golden rules of CPA diagram construction?
Work from left to right for
EST
.
Take the highest EST when activities meet.
Work from right to left for
LFT
.
Take the lowest LFT when activities meet.
View source
How can resources be managed in CPA?
Reorganize activities with
float
.
Reschedule tasks to optimize time.
Move resources from
critical
to non-critical tasks.
View source
What is the significance of the critical path in project management?
Identifies
essential activities
.
Helps minimize
project duration
.
Indicates where
delays
will impact the project.
View source