When you are making a new system you must consider it's benefit to a business. This is because there is no point wasting resources if it doesn't benefit the business proportionally
3 example benefits that a digital system is likely to provide?
Better userexperience
Improved datamanagement
Better collaboration
4 example drawbacks of a digital system?
Technicalproblems
High initial cost
Maintenanceexpenses
Dataprivacyconcerns
Avery common drawback of introducing digital systems is that many stakeholders may resist the change as humans dislike change
Risks are problems that may or may not occur during a project that may or may not cause the project to fail
4 common examples of risks of digital systems?
Organisation runs out of funds
Employees encounter setbacks
Employees die or become ill
The legislation regarding the system is changed
Constraints are problems that are known to exist, they may include?
Fixed funds
Fixed end date
Staff are skilled in certain things
MUst comply with legislation
Dependencies are where one task or activity relates to another
2 common examples of dependencies are?
Project depends on certain hardware or software
Requires another finished project
Dependencies mainly belong to one of the following four categories?
Mandatory
Discretionary
Exernal
Internal
Mandatory depedencies are where one activity requires another activity to be completed
Discretionary dependencies are where the order of activities has a preffered sequence such as a user interface before database and database before customer service
External dependencies are reliance on activities outside the project
Internal dependencies are reliance on activities within the project
Feasibility is the likelihood of a successful system weighed against the net benefit of a system
The Four Dependency Relationships are:
FtS
FtF
StS
StF
FtS is finish to start - It refers to one project needing to be complete for another to begin. It is similar to the waterfall project approach.
An example of FtS is needing a physical server to have been setup to put a database onto the physical server
StS means Start To Start, meaning that two or more activities cannot begin until they all do so at the same time.
FtF means Finish To Finish, meaning that two or more activities cannot complete until all have finished.
StF means Start to Finish - It is the rarest of dependencies and is where the successor work item does not finish until the predecessor work item starts.
An example of StF is waiting for regulatory approval (predecessor) before launching a marketing campaign (successor).
'The predecessor work item does not finish until the successor work item is finished.' What dependency relationship type is this?
Finish to finish
A lag can be used between tasks to slow development, as it will skip a period of time
A lead is when a project is begun before it's predecessor is finished
FtF is most similar to what project management approach?
agile
Start to start - meaning that the predessor must have begun for a successor to start
Start to start is often employed at the beginning of the project where many independent subsections can be began