3.3.4 CPA

Cards (13)

  • What is CPA?
    •  a project management tool that uses network analysis to plan complex and time-sensitive projects 
  • Key elements of CPA
    • A list of all activities required to complete the project
    • The time (duration) that each activity will take to complete
    • How each project activity depends on others
  • What does CPA show?
    • Order in which activities must be completed.
    • Longest path of project activities to the completion of the project
    • Earliest & latest  each project activity can start and finish without delaying completion of whole project.
    • Activities within a project that can be carried out simultaneously are identified
    • The critical project activities which if delayed will cause the project as a whole to over-run
    • Those project activities where some delay is acceptable without delaying the project as a whole
    • The shortest time possible to complete the project
  • What is a node?
    • a circle that represents activity is started or finished
    • split into three sections
    • The left half of the circle is the activity number 
    • top right section= EST based on the completion of the previous activity
    • bottom right section LFT by which the previous activity must be completed
  • Activities
    • An activity is a process or task within a project that takes time
    • Activities are  shown on the network diagram as a line which link nodes 
    • A description of the activity or a letter representing the activity is usually shown above the line
  • Duration
    • the length of time it takes to complete an activity
    • The duration is shown as a number of time units such as hours or days below the activity line
  • CPA
    .
    A) NODE
    B) ACTIVITY
    C) DURATION
    D) EST
    E) LFT
  • Critical Path
    • Critical path highlights activities that determine the length of the whole project.
    • If delayed, the project as a whole will be delayed
    • nodes where the EST and LFT are equal = Critical path
  • What is float time?
    • The total float refers specifically to spare time that is available so that the overall project completion is not delayed
    • Float time exists where there is a difference between the Earliest Start Time (EST and the Latest Finish Time (LFT)
  • How does float time help?
    • Transfer resources such as staff or machinery to more critical activities
    • Allow extra time to complete tasks to improve quality or allow for creativity
  • Calculation for float time
    • LFT for the activity - Duration of the activity - EST for the activity
  • Limitations of CPA
    • Very lengthy or complex projects involve a very large number of activities that have numerous dependencies.
    • Relies on estimates and forecasts.
    • Does not guarantee the success of a project .
    • Resources may not prove to be as flexible as hoped when managers identify float periods.
  • Limitations of CPA
    • Specialist network planning software may be required.
    • Layers of supervision may be required to manage different groups of activities within the project.
    • Significant research is required prior to the completion of network analysis.
    • Close and honest  working relationships with suppliers are essential.
    • Project managers - highly skilled and will need experience of working with complicated plans
    • Employees may require additional training in order to transfer to critical tasks
    • Machinery and other capital resources may require adaptatioN