COASTS CASE STUDY

Cards (10)

  • case study to show soft engineering as successful
    Bacton Gas Terminal
  • where is Bacton Gas terminal
    north coast of norfolk
  • outline what happened at bacton gas terminal
    2 million cubic metres of sand dredges from sea bed and used along 6km of coastline to nourish beach
  • how much sand was used
    2 million cubic metres
  • how long was the dune
    6km
  • why does bacon gas terminal need protecting
    -provides 1/3 of the UKs natural gas
    -when it was built it was 100m from the cliff edge, now some parts are just 10
  • what shows this project to be successful
    -dine initially thought to last 20 years, but recent analysis suggests twice as long
    -will also protect 2 nearby villages
  • why was this natural approach better than hard engineering
    protected 2 additional villages, whereas a sea wall would have given them huge flood risks
  • price of sea walls per metre
    £5000 per metre
  • cost of sandscaping at bacon gas terminal
    £20 million