A project management tool used to plan, schedule, and control complex projects
PERT
Developed in the 1950s by the U.S. Navy for the Polaris submarine missile program
Designed to facilitate the identification and management of the tasks necessary to complete a project
Events and Milestones
Specific points in time that mark the start or completion of one or more activities.
In PERT, events are typically represented as nodes in a network diagram.
Activities
Tasks that consume time and resources, represented by arrows in the network diagram.
Each activity has a preceding event and a succeeding event.
Time Estimates in PERT
Optimistic Time (O): The minimum possible time to complete the activity, assuming everything proceeds better than is normally expected.
Most Likely Time (M): The best estimate of the time required to complete the activity, assuming everything proceeds as normal.
Pessimistic Time (P): The maximum possible time to complete the activity, assuming everything goes wrong (excluding major catastrophes).
Network Diagram
A visual representation of the project's activities and events, showing the sequence and interdependencies of tasks. This is often a directed graph where nodes represent events and arrows represent activities.
Critical Path
The longest path through the network, which determines the shortest possible duration for the project. Any delay in activities on the critical path will delay the entire project.
Steps in PERT
1. Define the Project and Its Key Tasks
2. Sequence the Activities
3. Estimate the Time for Each Activity
4. Develop the Network Diagram
5. Calculate the Critical Path
6. Update the PERT Chart as the Project Progresses
Earliest Start (ES) and Earliest Finish (EF)
The earliest times an activity can start and finishwithout delaying the project.
Latest Start (LS) and Latest Finish (LF)
The latest times an activity can start and finish without delaying subsequent activities or the project.
Slack or Float
The amount of time an activity can be delayed without affecting the project completion date. Activities with zero slack are on the critical path.
Improved Planning and Scheduling
Clear visual representation of the project’s activities and their dependencies
Helping managers to plan and schedule more effectively.
Enhanced Decision-Making
Facilitates better decision-making by identifying the critical path and potential bottlenecks.
Flexibility
Can be applied to projects of any size and complexity
Making it a versatile tool in project management.
Risk Management
By incorporating time estimates with a range of scenarios, PERT allows managers to anticipate and plan for potential risks and uncertainties.
Time-Consuming and Complex
Large projects with many activities.
Subjectivity in Time Estimates
Over-focusing on it might lead to neglecting other significant activities that are not on the critical path but are still crucial to project success.
Static Nature
PERT charts can become outdated quickly as projects evolve.
Requiring constant updates to remain relevant and accurate.