PM FINALS

Cards (88)

  • PERT
    Program (Project) Evaluation and Review
    Technique
  • is a project management tool used to schedule, organize, and coordinate tasks within a project.

    Program (Project) Evaluation and Review
    Technique (PERT)

  • Program (Project) Evaluation and Review
    Technique (PERT):
    It is basically a method to analyse the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project.
  • PERT was invented by
    Booz Allen Hamilton, Inc. under contract to the United States Department
    of Defense's US Navy Special Projects Office in 1958
  • CPM was developed by the
    Dupont company & Remington-Rand-Univac
  • A part of the Polaris mobile submarine-launched ballistic missile project. This project was a direct response to the Sputnik crisis
  • T or F: PERT is used for large construction projects
    True
  • T or F: PERT and CPM were aware of the others existence from the 1960’s
    False
  • T or F: Both follow the same steps and use network diagrams
    True
  • T or F: Only PERt is used to plan the scheduling of individual activities that make up a project
    False
  • T or F: They can be used to determine the earliest/latest start and finish times for each activity
    True
  • T or F: CPM is probabilistic whereas PERT is deterministic
    False
  • T or F: In CPM, estimates of activity duration are based on historical data while in PERT, estimates are uncertain, and we talk of ranges of duration and the probability that an activity duration will fall into that range
    True
  • T or F: CPM concentrates on cost optimization while PERT concentrates on time control.
    True
  • T or F: PERT was developed in 1958 while CPM was developed in 1957
    True
  • T or F: CPM is event oriented while PERT is activity oriented
    False
  • T or F: PERT manages predictable activities while CPM manages unpredictable activities
    False
  • T or F: PERT is a three-time estimate and CPM is a single time estimate
    True
  • Examples of CPM & PERT Projects
    1.Construction of a new plant
    2. R&D of a new product
    3. NASA space exploration projects
    4. Movie productions
    5. Building a ship
    6. Government-sponsored projects for developing weapon
    systems
    7. Relocation of major facility
    8. Maintenance of nuclear reactor
    9. Installations of MIS
    10. Conducting an advertising campaigns
  • PERT is used when
    activity times are uncertain.
  • When do we use PERT?
    ▪ Determine the duration of the project.
    Decision making under risk (“P” for probabilistic)
  • is a point that marks the start or completion of one (or more) tasks.
    It consumes no time and uses no resources. It marks the completion of one (or
    more) task. It is not “reached” until all of the activities leading to that event
    have been completed.
    PERT event
  • an event (or events) that immediately precedes some other event without any other events intervening. It may be the consequence of more than one activity.
    Predecessor event
  • an event (or events) that immediately follows some other event without any other events intervening. It may be the consequence of more than one activity.
    Successor event
  • is the actual performance of a task. It consumes time, it requires
    resources (such as labor, materials, space, machinery), and it can be understood as representing the time, effort, and resources required to move from one event to another. It cannot be completed until the event preceding it has occurred.
    PERT activity
  • the minimum possible time required to accomplish a
    task, assuming everything proceeds better than is normally expected
    Optimistic time
  • the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
    Pessimistic time
  • the best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
    Most likely time
  • the average time the task would require if the task were repeated on a number of occasions over an extended period of time
    Expected time
  • the longest possible continuous pathway taken from the initial event to
    the terminal event.
    Critical Path
  • It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
    Critical Path
  • the time by which a predecessor event must be completed in order to
    allow sufficient time for the activities that must elapse before a specific PERT event is reached to be completed.
    Lead time
  • the earliest time by which a successor event can follow a specific PERT
    event.
    Lag time
  • measure of the excess time and resources available in achieving this event.
    Slack
  • It indicates ahead of schedule
    Positive slack
  • It indicates behind schedule
    negative slack
  • It indicates on schedule.
    zero slack
  • ES
    Early Start
  • maximum EF of all predecessor activities, unless the activity in question is the first activity, wherein ES is 0
    Early Start (ES)
  • EF
    Early Finish