Finals - Sad

Subdecks (1)

Cards (83)

  • Project Triangle - Cost, Scope, and Time
  • Project Triangle consist of; cost, scope, and time.
  • Project Planning - It identify all project tasks and estimate the completion time and cost of each.
  • Project Scheduling - It create specific timetable that shows task, task dependencies, and critical tasks that might delay the project.
  • Project Monitoring - Guiding, supervising, and coordinating the project teams' workload.
  • Project Reporting - create regular progress reports to management, users, and the project team itself.
  • Gantt Chart - It developed by the mechanical engineer and management consultant Henry L Gantt almost 100 years ago.
  • Gantt Chart - It shows planned and actual progress on a project wherein time displayed in horizontal axis and tasks displayed in vertical axis.
  • Program Evaluation Review Technique - It is developed by the U.S Navy to manage complex project.
  • Critical Path Method - It is similar with PERT but developed by private industry.
  • Work Breakdown Structure - It must clearly identify each task and include an estimated duration
  • Task or Activity - Any work that has beginning and an end and requires the use of company resources such as people, time, or money.
  • Task - These are the basic units of work that project manager plans, schedules, and monitors so they should be relatively small and manageable.
  • Two Steps Creating a Task:
    1. Listing the Task
    2. Estimating the Task Duration
  • Person-days - It is a unit of measurement if the tasks uses days.
  • Person-day - It represent the work that one person can complete in one day.
  • Factors that Affecting Duration:
    1. Project Size
    2. Human Resources
  • Project Size - Identifying all project task, from initial fact-finding to system implementation and how much time will be needed to perform each task
  • Human Resources - Assemble and guide a development team that has the skill and experience to handle the project.
  • Displaying the Work Breakdown Structure:
    1. Experience with Similar Projects
    2. Constraints
  • Experience with Similar Projects - It developed time and cost estimates based on the resources used for similar, previously developed information systems.
  • Constraints - These are the conditions, restrictions, or requirement that system must satisfy.
  • Five Task Box Element:
    1. Task Name
    2. Task ID
    3. Task Duration
    4. Start Day/Date
    5. Finish Day/Date
  • Task Name - it should be brief and descriptive.
  • Task ID - Can be a number or code that provides unique identification.
  • Task Duration - Amount of time it will take to complete a task.
  • Start Day/Date - Task is schedule to begin
  • Finish Day/Date - Task is scheduled to be completed.
  • Main Types of Task Patterns
    1. Dependent Tasks
    2. Multiple Successor Tasks
    3. Multiple Predecessor Tasks
  • Dependent Task - It happens when task must be completed one after another because one depends on the other.
  • Multiple Successor Tasks - It happens when several tasks can start at the same time.
  • Multiple Predecessor Tasks - It happens when a task requires two or more prior tasks to be completed before it can start.
  • Critical Path - It is a series of tasks which, if delayed, would affect the completion date of the overall project.
  • Monitoring and Control Techniques - Structure walkthrough
  • Maintaining a Schedule - most projects tune into some problems or delays
  • Project Status Meetings - Schedule regular meetings to update the team and discuss project status, issues, problems and opportunities.
  • Project Status report - It can be verbal or written and usually it handles potential problems can be difficult and Gantt charts are often included to show project status graphically.
  • Steps in Risk Management:
    1. Develop a Risk Management Plan
    2. Identify the Risk
    3. Analyze the Risk
    4. Risk Management Software
  • Develop a Risk Management Plant - This is the review of the project's scope, stakeholders, budget, schedule, and any other internal or external factor that might affect the projects.
  • Develop a Risk Management Plan - It defines the project roles and responsibilities, risk management methods and procedures, categories of risks, and contingency plans.