A situation where the contract is brought to an end
Discharge by Performance
1. The General Rule of Discharge by Performance
2. Divisible Contracts
3. Substantial Performance
4. Prevention of Full Performance
5. Acceptance of Part Performance
The General Rule of Discharge by Performance
Discharge by performance can only be done if the performance was complete and exact
The General Rule of Discharge by Performance
Cutter v Powell (1795)
Divisible Contracts
Where a contract can be split up into separate parts, if there is non-completion of one part of the contract then this will not be seen as a breach of the whole contract
Divisible Contracts
Ritchie v Atkinson (1808)
Substantial Performance
The doctrine of substantial performance states that payment of the amount appropriate to what has been done can be paid for the performance that was given
Substantial Performance
Dakin and Co. v Lee (1916)
Hoenig v Isaacs (1952)
Bolton v Mahadeva (1972)
Young v Thames Properties Ltd (1999)
Prevention of Full Performance
If one party prevents the other from carrying out the contract, then the innocent party can claim to be paid on a quantum meruit ('as much as it is worth') basis
Prevention of Full Performance
Planche v Colburn (1831)
Acceptance of Part-Performance
If one party has agreed that the other party need not complete the entire contract, then the contract must be paid on a quantum meruit ('as much as it is worth') basis
Acceptance of Part-Performance
Sumpter v Hedges (1898)
The Effect of a Term as to Time for Performance of a Contract
1. The Courts will regard a 'time' term as a condition where
2. If none of the above apply, then the 'time' term will be treated as a warranty rather than a condition
The Effect of a Term as to Time for Performance of a Contract
Charles Rickards Ltd v Oppenheim (1950)
Union Eagle Ltd v Golden Achievement Ltd (1997)
Section 52 of the Consumer Rights Act 2015 also discusses the time for performance of a contract
Applying our Knowledge to Practice Exam Questions
1. Question 1
2. Question 2
Discharge by Breach
1. Actual Breach
2. Anticipatory Breach
3. Remedies for a Breach
Actual Breach
When a party fails to perform their obligations under a contract, they may be sued for breach of contract
Repudiatory Breach
A breach of contract that is sufficiently serious that it entitled the innocent party to treat the contract as terminated
Repudiatory Breach
Stocznia Gdynia SA v Gearbulk Holidays (2009)
Anticipatory Breach
An anticipatory breach of contract occurs when a party to a contract gives notice in advance to the other party that they will not be performing or completing the contract
Anticipatory Breach
Hochester v de la Tour (1853)
Geden Operations Ltd v Drybulk Handy Holdings Inc. (Bulk Uruguay) (2014)
Applying our Knowledge to Practice Exam Questions
Question 3
Discharge by Frustration
1. The General Rule of Discharge by Frustration
2. Frustration is Allowed Where: there is impossibility, illegality or radical change of circumstances
ill not be carrying out the contract. This will amount to repudiation and the innocent party can treat the contract as at an end. However, uncertainty about future performance does not suffice for an anticipatory breach.
Repudiation
Words or conduct which evince an intention by the contracting party no longer to be bound by their contractual obligations
Self-induced impossibility
Conduct by the contracting party which puts it out of their power to perform their contractual obligations
Discharge by Breach - Remedies:
Discharge by Frustration - The General Rule of Discharge by Frustration:
Frustration
If a party to a contract was prevented from keeping their promise because of an unforeseeable, intervening event, then they are not liable for a breach of contract.
Frustration is Allowed Where: there is impossibility of performance, or the contract becomes illegal to perform.
Frustration is Not Allowed Where: there is self-induced frustration, the contract becomes less profitable, or the event being a foreseeable risk was mentioned in the contract.
Remedies for Frustration:
Discharge by Frustration - Impossibility of Performance:
Discharge by Frustration - The Contract Becoming Illegal to Perform:
Discharge by Frustration - The Contract Has Become Fundamentally Different:
When Will Frustration Not Apply - Self-Induced Frustration:
When Will Frustration Not Apply - The Contract Has Become Less Profitable:
When Will Frustration Not Apply - The Event Being a Foreseeable Risk or the Event was Mentioned in the Contract: