Sewerage system is normally designed for a design period of 25-30 years but it depends on: Fund available, Rate of interest, Life of material, Anticipated expansion of town, Ease/difficulty in expansion
Minimum velocity at which solids do not get deposited in the invert of the sewer. May not have SCV whole day but should have at least once in a day. Design velocity of flow is normally 0.6-0.9 m/s
Shields' Formula: Vs = k(8f(S-1)gd)^0.5 where, k = dimensionless constant, f = Darcy Weisbach friction factor, S = Specific gravity of sediments, g = gravity acceleration, d = diameter of grain
Joined by bell and spigot joints and collar joints
PCC is used for upto 60 cm diameter
Grade M20 is normally used
Merits: strong enough to withstand external and internal pressure, can be cast in site in required shape and size, Economical for medium and large size, Maintenance cost is low, Can be laid under water
Demerits: heavy to handle and transport, May be affected by acids and alkali and salt water, Most liable to crown corrosion
Sulphate present in sewage are converted into sulphide by bacteria and then to hydrogen sulphide gas. Further bacterial action forms sulphuric acid droplets at the crown. This makes crown uneven and its thickness reduces with respect to time which is called as crown corrosion.
General practice to lay sewer line between manholes and setting out from tail end or outfall and proceeding upwards
Method I: A offset line parallel to centre line is marked at a distance of (1/2 trench width + 0.6m). Pegs are driven along this line at an interval of 7.5-15m
Method II: Two vertical posts are driven into the ground at a known distance from centre line peg and one horizontal rail known as sight rail is fixed between these posts. Cord is driven between sight rails of consecutive posts.
Sewers are laid to correct alignment and gradient with the help of boning rods or sight rails or sometimes with level. Modified levels of invert are first obtained by adding a suitable vertical length to the invert levels marked on L-section. These modified levels are marked on sight rails either by fixing nails on sight rails or by adjusting the top of sight rails to the modified invert levels of sewer lines. The boning rod or traveler of same height is travelled on the cord to obtain required gradient.
Minimum depth above sewer is 0.9m and width is 0.6m. When depth exceeds 1.5-2.0m, timbering (support the side by sheeting and bracing) of trench is necessary. If high water table condition found during excavation, dewatering should be adopted.
Before placing the sewer pipe, the gradient of the bottom of the trench should be checked. Pipes are laid with their socket end faces at upgradient. Jointing are properly done and filled with cement mortar or bitumen. Normally collar or bell and spigot joints are used.
Water Test: Pipe lines are filled with water (plugging lower end and upper end with provision of air outlet in upper end and a provision of funnel in lower end). The water loss should not be greater than 2l/cm diameter of pipe per km length.
Air Test: Plug the sewer at both ends and from one end, air pressure equivalent to 100mm of water is given. If the pressure is maintained at 75 mm of water, the joint is assumed to be water tight.
Immediately done after successful testing. Backfilling soil should be free from pebbles, stones etc. Done in every 15 cm thickness, watered and evenly rammed. Should be about 60-90 cm above the crown and remain left for one week. After one week, backfilling is completed and filled 15 cm extra above the ground surface.
Non-putrescible waste excluding ashes, including combustible and non-combustible wastes such as paper, broken furniture, glass, plastic bottles, dismantled building materials
Improvement on dumping, solid wastes are dumped into low lying areas and covered by soil at least 20 cm thickness for each layer of 1-2 m (prevent from nuisance of flies and mosquitoes), the next layer is added only after 1 week, all the layers are compacted by moving vehicle or rollers
Costly plants and equipments are not required, residue are not remained for further disposal, pits of low lying areas are reclaimed
Requires more land, create foul gases and nuisance near the site, covering soil may not be available, may pollute ground water and surface water, insectisides are required to prevent fly nuisance
Solid wastes are separated into combustible and non-combustible, combustible wastes are burnt into properly constructed furnace or incinerator, hospital wastes are incinerated (in Nepal)
Hygienic method, no odor and dust nuisance, heat produced in incineration may be used for other heating purpose such as steam power, the produced clinker may be used in road construction, space requirement is less
High chimneys are required (to control air pollution), large initial cost, residue needs further disposal
The putrescible organic matters present in solid waste are decomposed aerobically or anaerobically and convert into humus and stable mineral compounds, hygienic method of converting the refuse into manure through the bacterial agencies, compost is widely used as a manure (rich in nitrogen content)
Trenches of 3-12 m length, 2-3 m wide and 1-2 m deep with a clear spacing of 2 m, organic solid waste is filled in layers of 15 cm, each layer is filled with 5 cm thick layer of night soil or animal excreta on semi liquid form for adding bacteria, top layer is covered by about 10 cm of good earth, biological action starts in 2-3 days and temperature may rises to 750C, waste gets stabilized and changed into brown coloured odorless powder (humus) after 4-6 months
Organic and putrescible matters are separated and dumped on the ground in the form of 0.6-1.0 m high, 6 m long and 1-2 m wide piles at about 60% moisture content, covered with animal dung, cattle urine, night soil etc, aerobic reaction needed and the temperature rises to 700C, pH should be adjusted to 7.2-7.4, after the temperature reaches 700C, pile is overturned and the moisture content and pH is maintained, temperature do not increase after certain time which indicates completion of bacterial activity i.e composting is completed, takes about 7-10 weeks and compost thus produced can be sold as a good fertilizer
Requires small area compare to trenching and open windrow, composting carried out in the closed room, solid waste stabilizes within 3-7 days, sprayers are used to adjust moisture content and the coils are used to make temperature constant at 700C, costly and done in large scale, operation involved: reception of refuse, segregation, shredding, stabilization, marketing the humus