AS 3600: 2018 specifies minimum requirements for the design and construction of concrete building structures and members that contain reinforcing steel or tendons, or both
Temporary structure used to support a permanent structure, material, plant, equipment and people until the construction of the permanent structure has advanced to the stage where it is self-supporting
A method of reinforcing concrete with high-strength steel strands typically referred to astendons
High-strength steel tendons are covered with duct to prevent them from bonding with the concrete
After the concrete has cured, the tendons are clamped on one end and jacked against the concrete on the other end until the required force is developed
Thinner slabs mean less concrete is required (i.e. slabs-on-ground 0% to 20% less concrete)
Can allow a significant reduction in building weight versus a conventional concrete building with the same number of floors (e.g. slabs-on-ground 70% to 90% less reinforcement bar)
Safe site access. This includes consideration of the size of the delivery truck and traffic management planning to ensure there are no delays on the day of the pour
Pump placement and accessibility needs to be considered
Rate of concrete placement should be specified so the supplier can plan production and schedule deliveries to match
Method that will be used to place the concrete, such as a chute, pump (type, size and length of the line), crane (kibble)
1. Check the concrete is not 'too wet' or 'too dry'
2. Make sure the concrete is properly mixed. It is important that the concrete is mixed at the correct speed in a transit mixer for at least two minutes immediately prior to discharge
3. The concrete should be placed as soon as possible. When transporting the mix, load carefully
4. If placing concrete straight from a truck, place vertically and never let the concrete fall more than one-and-a-half metres
Shaking or vibrating of the concrete to liquify it and expel any trapped air
The concrete settles, filling all the space in the forms
Properly compacted concrete is more dense, strong and durable. Off-form finishes will also be better
For concrete of average workability (i.e. slump of 80 mm) with a poker size between 25–75 mm, concrete should usually be vibrated for between 5 and 15 seconds
It is worse to UNDER-VIBRATE than to OVER-VIBRATE concrete
1. Instructions regarding proper timing, sequence and method in form stripping for back-propping and for form removal must be specific and clearly stated, referencing the expected concrete strength, curing time and temperature, design load and other specifications
2. Where back=propping is required, proper drawings and specific instructions must be provided instead of using such loose specifications as 50% or 70% back-propping, in note form. Back-propping plans should be submitted to the consulting Structural Engineer for consideration and approval
If the construction team is used to building with precast concrete panels products then the process of using GluLam beams and CLT panels is much the same. The difference is that the erection will be quicker because the structure can be built using one trade instead of three.
Poured into a reusable mould or 'form', cured in a controlled environment, then lifted into place
Common production methods include tilt-up (poured on site) and precast (poured off site and transported to site). Each method has advantages and disadvantages and choice is determined by site access, availability of local precasting facilities, required finishes, and design demands
Can provide a fast building process. However, careful design and planning is needed to ensure the openings and other details meet the design needs
Costs can range in the upper end of high-mass solutions. Reduced construction times and need for on-site trades can offset this to some extent
Economies of scale and repetition can further reduce costs